Project name: Development-research BioPark for animal production and biotechnology - KK.01.1.1.09.0020
User name: Josip Juraj Strossmayer University in Osijek, Faculty of Agrobiotechnical Sciences Osijek
Duration of the project: 32 months - 03.05.2021. - 25.12.2023.
Total value of the project: HRK 3,608,327.49
EU co-financing of the project: HRK 3,608,327.49
The implementation of the project will create the project documentation necessary for the implementation of the IRI infrastructure project, which includes investing in organizational reform and building and equipping the faculty's experimental site (BioPark) at 3/8 k.o. Antunovac. The implementation of the project for creating project documentation and the implementation of the IRI infrastructure project will enable the applicant to further develop research, implement innovations, encourage cooperation with other scientific organizations, and connect the applicant with business entities.
The following project activities are planned for the subject project:
Creation of design and technical documentation
Creating a Feasibility Study with a cost-benefit analysis
Implementation of horizontal principles
Project management
Promotion and visibility
The target group of the project are:
Members of the project (Prof. Krunoslav Zmaić, PhD, dean and project manager) and research team (Prof. Tihomir Florijančić, PhD, head of the research team) who will contribute to the successful implementation of the project with their knowledge and experience.
Employees of the applicant who will participate in the activity of implementing the horizontal principles.
The project is co-financed by the funds of the EUROPEAN FUND FOR REGIONAL DEVELOPMENT within the OPERATIONAL PROGRAM COMPETITIVENESS AND COHESION 2014-2020, call "PREPARATION OF IRI INFRASTRUCTURE PROJECTS"
For more information on EU funds, visit the website of the Ministry of Regional Development and Funds of the European Union www.strukturnifondovi.hr.
Activities:
AUGUST 2021.
The procurement process for the services of ensuring the visibility and promotion of the project was initiated and a graphic studio was contracted to create the logo, banner and cover of the project documentation. Project visibility elements have been placed on the applicant's website.
SEPTEMBER 2021
The 1st meeting of the project team was held and it was determined that the 1st ZNS was fully approved by SAFU. Procurement procedures for the services of Education - combating discrimination and raising awareness and Education on measures of sustainable development have been launched and external experts have been selected to conduct the training in October.
OCTOBER 2021
The 2nd meeting of the project team was held and two trainings were held:
One-day education on measures of sustainable development (measures of better energy efficiency and savings)
One-day training on combating discrimination and raising the level of awareness related to accessibility for people with disabilities
A draft of procurement documentation was prepared for the procurement of project-technical documentation for the projects "Scientific research center for vines and wine Mandićevac KK.01.1.1.09.0021" and "Development research BioPark for animal production and biotechnology KK.01.1.1.09". 0020".
The project is co-financed by the funds of the EUROPEAN FUND FOR REGIONAL DEVELOPMENT within the OPERATIONAL PROGRAM COMPETITIVENESS AND COHESION 2014-2020, call "PREPARATION OF IRI INFRASTRUCTURE PROJECTS"
For more information on EU funds, visit the website of the Ministry of Regional Development and Funds of the European Union www.strukturnifondovi.hr.
NOVEMBER 2021
The request for reimbursement of funds ZNS-02 for the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology was submitted by the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The selected specialist for public procurement prepared the Procurement Documentation for the procurement of Project-Technical Documentation, which was submitted for public consultation and prior control at SAFU.
DECEMBER 2021.
The request for reimbursement of ZNS-02 funds for the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology was refined. 14.12.2021. a meeting of the project team was held.
JANUARY 2022.
In the Payments and refunds module for the project KK.01.1.1.09.0020 - Development-research BioPark for animal production and biotechnology, the payment was recorded in accordance with the approved ZNS No. 2. The creation of project-technical documentation is in the status of review and control.
FEBRUARY 2022.
The 4th meeting of the project team related to the creation of project technical documentation was held. A request for reimbursement of ZNS-03 funds has been submitted.
MARCH 2022.
The competent institution approved the request for reimbursement of ZNS-03 funds of the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The 5th meeting of the project team was held.
APRIL 2022.
The 6th meeting of the project team was held prior to the preparation of Request for reimbursement of funds number 4, with the aim of determining the activities that need to be undertaken by the end of the reporting period, which ends on 05/03/2022. The procurement procedure was repeated and a new Decision on selection in the procurement of design and technical documentation was adopted.
MAY 2022.
The 7th meeting of the project team was held. 18.5. was submitted to ZNS no. 4 and a contract was signed for the service of creating project technical documentation.
JUNE 2022.
The competent institution approved the request for reimbursement of ZNS-04 funds of the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The 8th meeting of the project team was held.
JULY 2022.
The 9th meeting of the project team was held. The procurement procedure was carried out and the decision was made on the selection in the procurement of Feasibility Study and cost benefit analysis.
SEPTEMBER 2022.
The 10th meeting of the project team was held. A project manager has been hired. The competent institution approved the request for reimbursement of ZNS-05 funds of the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek.
OCTOBER 2022
The 11th meeting of the project team was held, project technical and study documentation is being prepared.
NOVEMBER 2022
The 12th meeting of the project team was held and a request for a major contract amendment was submitted. The request for reimbursement of funds ZNS-06 for the project KK.01.1.1.09.0020 - Development-research BioPark for animal production and biotechnology was submitted by the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek.
DECEMBER 2022.
Telephone meetings of the project team were held and the request for reimbursement of ZNS-06 funds for the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology was approved. A Notice was issued on the established special conditions and connection conditions.
JANUARY 2023
The 15th meeting of the project team was held.
FEBRUARY 2023.
A major contract amendment was approved and the project was extended to 26 months. The request for reimbursement of funds ZNS-07 for the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology was submitted by the beneficiary Josip Juraj Strossmayer University in Osijek, Faculty of Agrobiotechnical Sciences Osijek.
MARCH 2023
The competent institution approved the request for reimbursement of funds from ZNS-07 project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology. Representatives of the Central Agency for Financing and Contracting of Programs and Projects of the European Union (SAFU) 31.3.2023. they carried out an on-site inspection.
APRIL 2023.
During the field control, the competent institution established that there were no changes in the implementation of the project that PT2 was not informed about. During the field check, no differences were observed between the documentation kept by the User and the documentation received in PT2. During the on-site check, it was concluded that the visibility marks on the documentation are in accordance with the Grant Agreement and guidelines for fund beneficiaries.
MAY 2023.
The Request for a major amendment to the contract 3.0 for the project KK.01.1.1.09.0020 - Development-research BioPark for animal production and biotechnology was submitted. The 16th meeting of the project team was held.
JUNE 2023.
The request for reimbursement of funds ZNS-08 for the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology was submitted by the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. Telephone meetings of the project team were held.
JULY 2023
The competent institution approved the request for reimbursement of ZNS-08 funds of the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The 17th, 18th and 19th meeting of the project team was held.
AUGUST 2023.
The request for reimbursement of funds ZNS-09 for the project KK.01.1.1.09.0020 - Development-research BioPark for animal production and biotechnology was submitted by the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The 20th meeting of the project team was held.
SEPTEMBER 2023
The competent institution approved the request for reimbursement of funds from ZNS-09 project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user Josip Juraj Strossmayer University in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The 21st meeting of the project team was held.
OCTOBER 2023
The project technical documentation was prepared and the Osijek-Baranja County, Administrative Department for Spatial Planning, Construction and Environmental Protection issued a building permit for the construction of the development-research BioPark for animal production and biotechnology.
NOVEMBER 2023
The request for a major amendment to contract 4.0 for the project KK.01.1.1.09.0020 - Development-research BioPark for animal production and biotechnology was submitted by the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. Also, the User submitted a request for reimbursement of ZNS-10 funds.
DECEMBER 2023.
The competent institution approved the request for reimbursement of ZNS-10 funds of the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek. The competent institution approved the request for a major amendment to contract 4.0 for the project KK.01.1.1.09.0020 - Development and research BioPark for animal production and biotechnology of the user University J.J. Strossmayer in Osijek, Faculty of Agrobiotechnical Sciences Osijek.